FIRST PEOPLES' GATHERING HOUSE MONTHLY UPDATE

December 8, 2021

DESIGN UPDATE

During the month of November, a cost estimate update was prepared based on the latest design of the new building to provide insight on market pricing. Unstable market conditions and supply chain issues are impacting construction costs.  

CONSTRUCTION UPDATE

Demolition of the Strand Hall Annex temporary structure is underway in preparation for the new First Peoples’ Gathering House. To demonstrate sustainable construction practice, where possible, materials are being salvaged for re-use and remaining demolition wastes are being separated into different streams with the goal to divert materials from the landfill.

COMMITTEE UPDATE

The Steering Committee will be meeting in December to discuss costing and schedule updates on the project.

Sign up to receive our monthly updates.