The CALENDAR Procedure

Concepts


Type of Calendars
PROC CALENDAR can produce two kinds of calendars: schedule and summary.

Use a ... if you want to ... and can accept this restriction
schedule calendar schedule activities around holidays and nonwork periods cannot calculate sums and means

schedule activities that last more than one day
summary calendar calculate sums and means activities can last only one day

Note:   PROC CALENDAR produces a summary calendar if you do not use a DUR or FIN statement in the PROC step.  [cautionend]


Schedule Calendar

Definition

A report in calendar format that shows when activities and holidays start and end.

Required Statements

You must supply a START statement and either a DUR or FIN statement.

Use this statement . . . to specify a variable whose value indicates the . . .
START starting date of an activity
DUR* duration of an activity
FIN* ending date of an activity
*Choose one of these. If you do not use a DUR or FIN statement CALENDAR assumes you want to create a summary calendar report.


Examples

See Simple Schedule Calendar -- 7-Day Default Calendar , Advanced Schedule Calendar , as well as Schedule Calendar with Holidays -- 5-Day Default , Schedule Calendar Containing Multiple Calendars , Multiple Schedule Calendars with Atypical Workshifts (Separated Output) , Multiple Schedule Calendars with Atypical Workshifts (Combined and Mixed Output) , Schedule Calendar, Blank or with Holidays , and Calculating a Schedule Based on Completion of Predecessor Tasks


Summary Calendar

Definition

A report in calendar format that displays activities and holidays that last only one day and that can provide summary information in the form of sums and means.

Required Statements

You must supply a START statement. This statement identifies the variable in the activities data set that contains an activity's starting date.

Multiple Events on a Single Day

A summary calendar report can display only one activity on a given date. If more than one activity has the same START value, therefore, only the last observation that was read is used. In such situations, you may find PROC SUMMARY useful in collapsing your data set to contain one activity per starting date.

Examples

See Simple Summary Calendar , Summary Calendar with MEAN Values By Observation , and Multiple Summary Calendars with Atypical Workshifts (Separated Output)


The Default Calendars

Description

PROC CALENDAR provides two default calendars for simple applications. You can produce calendars without having to specify detailed workshifts and weekly work patterns if your application can use one of two simple work patterns. Consider using a default calendar if

Default Calendar Settings and Examples
If scheduled work days are Then set INTERVAL= By default DAYLENGTH= So work periods are Shown in Example
7 (M-Sun) DAY 24 24-hour days 2
5 (M-F) WORKDAY 8 8-hour days 1


When You Unexpectedly Produce a Default Calendar

If you want to produce a specialized calendar, but do not provide all the necessary information, PROC CALENDAR attempts to produce a default calendar. These errors cause PROC CALENDAR to produce a calendar with default features:


Examples

See the 7-day default calendar in Simple Schedule Calendar and the 5-day default calendar in Schedule Calendar with Holidays -- 5-Day Default


Calendars and Multiple Calendars

Definitions

calendar
a logical entity that represents a weekly work pattern, which consists of weekly work schedules and daily shifts. PROC CALENDAR contains two default work patterns: 5-day week with an 8-hour day or a 7-day week with a 24-hour day. You can also define your own work patterns using CALENDAR and WORKDAYS data sets.

calendar report
a report in calendar format that displays activities, holidays, and nonwork periods. A calendar report can contain multiple calendars in one of three formats

separate
Each identified calendar prints on separate output pages.

combined
All identified calendars print on the same output pages and each is identified.

mixed
All identified calendars print on the same output pages but are not identified as belonging to separate calendars.

multiple calendar
a logical entity that represents multiple weekly work patterns.


Why Create Multiple Calendars

Create a multiple calendar if you want to print a calendar report that shows activities that follow different work schedules or different weekly work patterns. For example, a construction project report might need to use different work schedules and weekly work patterns for work crews on different parts of the project.

Another use for multiple calendars is to identify activities so that you can choose to print them in the same calendar report. For example, if you identify activities as belonging to separate departments within a division, you can choose to print a calendar report that shows all departmental activities on the same calendar.

And finally, using multiple calendars, you can produce separate calendar reports for each calendar in a single step. For example, if activities are identified by department, you can produce a calendar report that prints the activities of each department on separate pages.

How to Identify Multiple Calendars

Because PROC CALENDAR can process only one data set of each type (activities, holidays, calendar, workdays) in a single PROC step, you must be able to identify for PROC CALENDAR which calendar an activity, holiday, or weekly work pattern belongs to. Use the CALID statement to specify the variable whose values identify the appropriate calendar. This variable can be numeric or character.

You can use the special variable name _CAL_ or you can use another variable name. PROC CALENDAR automatically looks for a variable named _CAL_ in the holiday and calendar data sets, even when the activities data set uses a variable with another name as the CALID variable. Therefore, if you use the name _CAL_, at least in your holiday and calendar data sets, you can more easily reuse these data sets for different calendar applications.

Using Holidays or Calendar Data Sets with Multiple Calendars

When using a holidays or calendar data set with multiple calendars, PROC CALENDAR treats the variable values in the following way:


Types of Reports That Contain Multiple Calendars

Because you can associate different observations with different calendars, you can print a calendar report that shows activities that follow different work schedules or different work shifts or that contain different holidays. You can

As an example, consider a calendar that shows the activities of all departments within a division. Each department can have its own calendar identification value and, if necessary, can have individual weekly work patterns, daily work shifts, and holidays.

If you place activities associated with different calendars in the same activities data sets, you use PROC CALENDAR to produce calendar reports that print

The multiple-calendar feature was added specifically to enable PROC CALENDAR to process the output of PROC CPM in SAS/OR software, a project management tool. See Calculating a Schedule Based on Completion of Predecessor Tasks .

How to Identify Calendars with the CALID Statement and the Special Variable _CAL_

To identify multiple calendars, you must use the CALID statement to specify the variable whose values identify which calendar an event belongs with. This variable can be numeric or character.

You can use the special variable name _CAL_ or you can use another variable name. PROC CALENDAR automatically looks for a variable named _CAL_ in the holiday and calendar data sets, even when the activities data set uses a variable with another name as the CALID variable. Therefore, if you use the name _CAL_, at least in your holiday and calendar data sets, you can more easily reuse these data sets for different calendar applications.

When You Use Holidays or Calendar Data Sets

When you use a holidays or calendar data set with multiple calendars, PROC CALENDAR treats the variable values in the following way:


Examples

Schedule Calendar Containing Multiple Calendars , Multiple Schedule Calendars with Atypical Workshifts (Separated Output) , Multiple Schedule Calendars with Atypical Workshifts (Combined and Mixed Output) , and Multiple Summary Calendars with Atypical Workshifts (Separated Output)


Input Data Sets
You may need several data sets to produce a calendar, depending on the complexity of your application. PROC CALENDAR can process one of each of four data sets. See Four Possible Input Data Sets for PROC CALENDAR .

Four Possible Input Data Sets for PROC CALENDAR
Data Set Description Specify with the . . .
activities Each observation contains information about a single activity. DATA= option
holidays Each observation contains information about a holiday HOLIDATA= option
calendar Each observation defines one weekly work schedule. CALEDATA= option
workdays Each variable represents one daily schedule of alternating work and nonwork periods. WORKDATA= option


Activities Data Set

Purpose

The activities data set, specified with the DATA= option, contains information about the activities to be scheduled by PROC CALENDAR. Each observation describes a single activity.

Requirements and Restrictions


Structure

Each observation in the activities data set contains information about one activity. One variable must contain the starting date. If you are producing a schedule calendar, another variable must contain either the activity duration or finishing date. Other variables can contain additional information about an activity.

If a variable contains an activity's . . . Specify it with the . . . For this type of calendar. . .
starting date START statement Schedule Summary
duration DUR statement Schedule
finishing date FIN statement Schedule


Multiple Activities per Day in Summary Calendars

A summary calendar can display only one activity on a given date. If more than one activity has the same START value, therefore, only the last observation read is used. In such situations, you may find PROC SUMMARY useful to collapse your data set to contain one activity per starting date.

Examples

Every example in the Examples section uses an activities data set.


Holidays Data Set

Purpose

You can use a holidays data set, specified with the HOLIDATA= option, to


Structure

Each observation in the holidays data set must contain at least the holiday starting date. A holiday lasts only one day unless a duration or finishing date is specified. Supplying a holiday name is recommended, though not required. If you do not specify which variable contains the holiday name, PROC CALENDAR uses the word DATE to identify each holiday.

If a variable contains a holiday's . . . Then specify it with this statement . . .
starting date HOLISTART
name HOLIVAR
duration HOLIDUR
finishing date HOLIFIN


No Sorting Needed

You do not need to sort or index the holidays data set.

Using SAS Date Versus SAS Datetime Values

PROC CALENDAR calculates time using SAS datetime values. Even when your data are in DATE. format, the procedure automatically calculates time in minutes and seconds. If you specify only date values, therefore, PROC CALENDAR prints messages similar to the following ones to the SAS log:
NOTE: All holidays are assumed to start at the
time/date specified for the holiday variable
and last one DTWRKDAY. WARNING: The units of calculation are SAS datetime
values while all the holiday variables are
not. All holidays are converted to SAS
datetime values.

Create a Generic Holidays Data Set

If you have many applications that require PROC CALENDAR output, consider creating a generic holidays data set that contains standard holidays. You can begin with the generic holidays and add observations that contain holidays or nonwork events specific to an application.
CAUTION:
Do not schedule holidays during nonwork periods. Holidays defined in the HOLIDATA= data set cannot occur during nonwork periods defined in the work schedule. For example, you cannot schedule Sunday as a vacation day if the work week is defined as Monday through Friday. When such a conflict occurs, the holiday is rescheduled to the next available working period following the nonwork day.  [cautionend]

Examples

Every example in the Examples section uses a holidays data set.


Calendar Data Set

Purpose

You can use a calendar data set, specified with the CALEDATA= option, to specify work schedules for different calendars.

Structure

Each observation in the calendar data set defines one weekly work schedule. The data set created in the DATA step shown below defines weekly work schedules for two calendars, CALONE and CALTWO.
data cale;
   input _sun_ $ _mon_ $ _tue_ $ _wed_ $ _thu_ $ /
         _fri_ $ _sat_ $ _cal_ $ d_length time6.;
   datalines;
holiday workday workday workday workday
workday holiday calone 8:00
holiday shift1 shift1 shift1 shift1
shift2 holiday caltwo 9:00
;

The variables in this calendar data set consist of

_SUN_ through _SAT_
the name of each day of the week that appears in the calendar. The values of these variables contain the name of workshifts. Valid values for workshifts are

_CAL_
the CALID (calendar identifier) variable. The values of this variable identify different calendars. If this variable is not present, the first observation in this data set defines the work schedule that is applied to all calendars in the activities data set.

If the CALID variable contains a missing value, the character or numeric value for the default calendar ( DEFAULT or 0) is used. See The Default Calendars for further details.

D_LENGTH
the daylength identifier variable. Values of D_LENGTH indicate the length of the standard workday to be used in calendar calculations. You can set the workday length either by placing this variable in your calendar data set or by using the DAYLENGTH= option.

Missing values for this variable default to the number of hours specified in the DAYLENGTH= option; if the DAYLENGTH= option is not used, the day length defaults to 24 hours if INTERVAL=DAY, or 8 hours if INTERVAL=WORKDAY.


Using Default Workshifts Instead of a Workdays Data Set

You can use a calendar data set with or without a workdays data set. Without a workdays data set, WORKDAY in the calendar data set is equal to one of two standard workdays, depending on the setting of the INTERVAL= option:

If INTERVAL= Then the work-shift begins at . . . And the day length is . . .
DAY 00:00 24 hours
WORKDAY 9:00 8 hours

You can reset the length of the standard workday with the DAYLENGTH= option or a D_LENGTH variable in the calendar data set. You can define other work shifts in a workdays data set.

Examples

Multiple Schedule Calendars with Atypical Workshifts (Separated Output) , Multiple Schedule Calendars with Atypical Workshifts (Combined and Mixed Output) , and Summary Calendar with MEAN Values By Observation feature a calendar data set.


Workdays Data Set

Purpose

You can use a workdays data set, specified with the WORKDATA= option, to define the daily workshifts named in a CALEDATA= data set.

Use Default Work Shifts or Create Your Own?

You do not need a workdays data set if your application can use one of two default work shifts:

If INTERVAL= Then the work-shift begins at . . . And the day length is. . .
DAY 00:00 24 hours
WORKDAY 9:00 8 hours

See the INTERVAL= option .

Structure

Each variable in the workdays data set contains one daily schedule of alternating work and nonwork periods. For example, this DATA step creates a data set that contains specifications for two work shifts:
data work;
   input shift1 time6. shift2 time6.;
   datalines;
7:00  7:00
12:00 11:00
13:00   .
17:00   .
;

The variable SHIFT1 specifies a 10-hour workday, with one nonwork period (a lunch hour); the variable SHIFT2 specifies a 4-hour workday with no nonwork periods.

How Missing Values Are Treated

The missing values default to 00:00 in the first observation and to 24:00 in all other observations. Two consecutive values of 24:00 define a zero-length time period, which is ignored.

Examples

See Multiple Schedule Calendars with Atypical Workshifts (Separated Output)


Missing Values in Input Data Sets
Treatment of Missing Values in PROC CALENDAR summarizes the treatment of missing values for variables in the data sets used by PROC CALENDAR.

Treatment of Missing Values in PROC CALENDAR
Data set

Variable Treatment of missing values
Activities (DATA=) CALID default calendar value is used

START


observation is not used

DUR 1.0 is used

FIN START value + daylength is used

VAR if a summary calendar or the MISSING option is specified, the missing value is used; otherwise, no value is used

SUM, MEAN 0

Calendar (CALEDATA=) CALID default calendar value is used

_SUN_ through _SAT_ corresponding shift for default calendar is used

D_LENGTH if available, DAYLENGTH= value is used; otherwise, if INTERVAL=DAY, 24:00 is used; otherwise 8:00 is used

SUM, MEAN 0

Holiday (HOLIDATA=) CALID all holidays apply to all calendars

HOLISTART observation is not used

HOLIDUR if available, HOLIFIN value is used instead of HOLIDUR value; otherwise 1.0 is used

HOLIFIN if available, HOLIDUR value is used instead of HOLIFIN value; otherwise, HOLISTART value + day length is used

HOLIVAR no value is used

Workdays (WORKDATA=) any for the first observation, 00:00 is used; otherwise, 24:00 is used