A
is the successor of an outcome of
stage B
, then stage A
should occur to the right of stage
B
. The MOVE
statement can be used to change the order.
If the keyword BEFORE is used, stage1 becomes the new
successor for all immediate predecessors of stage2, and
stage2 becomes the new successor for all outcomes of
stage1. An outcome is said to be an immediate
predecessor of a stage if the stage is the successor of that
outcome. Similarly, if the keyword AFTER is used, the old leftmost
(in previous order) successor of outcomes for stage2 becomes
the new successor for all outcomes of stage1 and the new
successor of all outcomes of stage2 is stage1.
There are two limitations: the END stage cannot be moved, and no stage can be moved after the END stage. In practice, any stage after the END stage is useless.