Re: question regarding 5.0.8 -> 5.0.11 upgrade
----- "Michael A. Jastremski" <jastrems@isc.upenn.edu> wrote:
| Good afternoon,
|
| We are planning an upgrade of our multi-server environment in the next
| month or so.
| I'm writing today to ask a few questions ..
|
| - Have you upgraded to 5.0.11 from a prior 5.0.X release? If so, was
| this a multi-server environment?
Yes in anmulti-server environment, with 3 ldap servers, 8 production mailbox servers, 2 spares.
| - How long did the process take? How much time was initially
| allocated?
Allocate 2 hours, usually takes 1.5 hours.
| - Any new problems with 5.0.11 ?
Why not go to 5.0.15?
We upgrade in test environment first ( 2 ldap servers, 2 mailbox servers). No problem found for the upgrade process.
5.0.15 production system upgrade is scheduled this coming weekend from 5.0.12 to 5.0.15.
| - How many users/gigabytes were involved in your upgrade?
Average 5000 users per server, 1.5 TB used space in /opt/zimbra/store.
| - Anything you'd do differently a second time around?
We've done it 10 times over (starting from 5.0.3). Most upgrade and post-upgrade are managed by configuration management ( things that would not be kept by upgrade, such as
skin, java policy if you use kerberos) and scripts (disable/enabling monitoring, put up outage page on webmail, post-upgrade tests etc).
Xueshan
|